| 1 | Tunneling & Segment Production Progress | CSIA T2 Metro Station |
| Tunnel CSIA T2 to Sahar Road Station (Downline): |
| Permanat Ring: Total Progress - 491, Scope - 491 |
| Completed |
| Permanat Ring: Total Progress - 491, Scope - 491 |
| Completed |
| Tunnel MVS to CSIA T1 (Upline): |
| Permanat Ring: Total Progress - 910, Scope - 910 |
| Completed |
| Tunnel MVS to CSIA T1 (Downline): |
| Permanat Ring: Total Progress - 892, Scope - 892 |
| Completed |
| Sahar Road Station to CSMIA |
| Domestic Airport Station (Downline) |
| Permanat Ring: Total Progress - 1080, Scope - 1080 |
| Segment Production Progress: |
| Permanent Rings: Total progress - 4949, Scope - 4949 |
| 2 | Excavation | CSIA T1 Metro station |
| Total progress - 268971 Cum. Scope - 268471 Cum. (Work in progress) |
| Sahar road Station |
| Total progress - 322478 Cum. Scope - 322478 Cum. (Completed) |
| CSIA T2 Metro Station |
| Total progress - 468642 Cum. Scope - 468642 Cum. (Completed) |
| 3 | Base Slab Progress | CSIA T1 Metro station: |
| Base Slab Completed. |
| Concourse Slab: Total progress - 196 m. Scope - 198 m. (Work in progress) |
| Concourse to Roof Slab: Total progress - 370 m. Scope - 390 m. (Work in progress) |
| Roof Slab: Total progress - 196 m. Scope - 198 m. (Work in progress) |
| CSIA T2 Metro Station: |
| Base Slab Completed. |
| Concourse Slab: Total progress - 311 m. Scope - 314 m. (Work in progress) |
| Concourse to Roof Wall: Total progress - 499 m. Scope - 541 m. (Work in progress) |
| Roof Slab: Total progress - 311 Cum. Scope - 314 m. (Work in progress) |
| Sahar Road Metro station: |
| Base Slab Completed. |
| Concourse Slab: Total progress - 220 m. Scope - 220 m. (Completed) |
| Concourse to Roof Slab: Total progress - 328 m. Scope - 328 m. (Completed) |
| Roof Slab: Total progress - 220 Cum. Scope - 220 m. (Completed) |
| 4 | Secant Piling Progress | CSIA T1 Metro station |
| Secant piles: Total progress - 808, Scope - 808 |
| Micro piles: Total progress - 154, Scope - 154 |
| Sahar road Station |
| Secant piles: Total progress - 1121, Scope - 1121 |
| Subway secant piles: Total progress - 67, Scope - 67 |
| CSIA T2 Metro Station |
| Secant piles: Total progress - 1298, Scope - 1298 |
| 5 | Rehabilitation & Resettlement | ______ |
| 6 | Building condition Survey | Pre-condition survey this week - 0 |
| Total Progress - 60 |
| Scope - 60 |
| 7 | Tree Cutting/transplantation | CSIA T1 - Total progress - 3 , Scope - 3 , Completed |
| Transplantation - 60 out of 112 |
| Sahar Rorad - Total progress - 4 , Scope - 4 , Completed |
| Transplantation - 177 out of 226 |
| CSIA T2 - Total progress - 0 , Scope - 0 , Completed |
| Transplantation - 4 out of 4 completed |
| 8 | Traffic Diversion | SAHAR ROAD STATION: |
| Road diversion: Stage-1 Completed |
| Subway completed |
| Sahar Shadow Road: |
| Commissioned on 27th July 2018. |
| Caping beam & Flood Wall: Completed |
| CSIA T2 Metro Station: |
| Internal Road: Completed. |
| Ancillary Works for TBM Launching: Completed |
| 9 | Geo-technical investigation | SAHAR Road Metro station |
| Completed |
| Sahar Road to International Station |
| CSIA T1 Metro Station |
| Completed |
| CSIA T2 Metro Station |
| Completed |
| 10 | Barricading | SAHAR Road Metro station |
| All construction Works is going on within |
| secured barricading area . |
| CSIA T1 Metro station |
| Completed |
| CSIA T2 Metro station |
| Completed |
| Construction Depot JVLR (GI Sheets) |
| Completed |