Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • eTender - CPPP
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • About MMRC Vigilance
    • Functions of the CVO
    • Vigilance Complaints
    • Notice
    • Contact Us
    • Vigilance Awareness Week
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
    • RISK ASSESSMENT & MANAGEMENT POLICY
    • WHISTLE BLOWER POLICY
    • CORPORATE SOCIAL RESPONSIBILITY POLICY
Flash News
MMRC

Flash News

MMRC E-Calendar 2025
Design, Engineering, Supply, Installation, Testing, Commissioning and Comprehensive Operation & Maintenance of Roof Top Solar PV Project and associated support structure works on RESCO Model for a Period of 25 Years on Aarey Station & Depot Buildings of Mumbai Metro Line -3 (MML-3) Project.
MMRC extends service hours for election day
Implementation of Multi Modal Integration Facilities at Six Underground Metro Stations viz. BKC, Bandra Colony, Santacruz, Chatrapati Shivaji Maharaj Domestic Airport (CSIA T1), Sahar Road & Chatrapati Shivaji Maharaj International Airport (CSIA T2) of Mumbai Metro Line ‐ 3
Implementation of Multi Modal Integration Facilities at Six Underground Metro Stations viz. BKC, Bandra Colony, Santacruz, CSIA T1, Sahar Road & CSIA T2 of Mumbai Metro Line-3 project
Implementation of Multi Modal Integration Facilities at Six Underground Metro Stations viz. BKC, Bandra Colony, Santacruz, Chatrapati Shivaji Maharaj Domestic Airport (CSIA T1), Sahar Road & Chatrapati Shivaji Maharaj International Airport (CSIA T2) of Mumbai Metro Line ‐ 3
List of NOC's issued till 30.09.2024
Property Development on Plot bearing CTS No 1987, 1988 at Nariman Point, A Ward, Mumbai (Maharashtra, India) on Long-Term Lease Basis
Invitation to Roadshow for Property Development on plot bearing CTS No. 1987, 1988 at Nariman Point, A Ward, Mumbai (Maharashtra, India) on Long-term Lease Basis
Supplying & fixing precast SFRC heavy duty slab for inspection pathways in Aarey colony car depot of Mumbai Metro Line ‐3 project
  1. Home
  2. Tenders
  3. Project Status

Project Status

MMRC

The MML-3 Project is divided into 18 main packages of ‘Project’ & ‘System’ wings.

Package wise status of the project is as under:

PackagesNature of WorkName of ContractorAmtStatusTarget for Contract Award
Package 1Civil Works – Tunnels & StationsL&T-STEC JVRs. 2,988.53 crLetter of Acceptance Issued to ContractorAwarded
Package 2Civil Works – Tunnels & StationsHCC-MMS JVRs. 2,521.89 crLetter of Acceptance Issued to ContractorAwarded
Package 3Civil Works – Tunnels & StationsM/S DOGUS-SOMARs. 2,557.84 crLetter of Acceptance Issued to ContractorAwarded
Package 4Civil Works – Tunnels & StationsM/S CEC-ITD CEM-TPL JVRs. 2,830.10 crLetter of Acceptance Issued to ContractorAwarded
Package 5Civil Works – Tunnels & StationsM/S J. Kumar-CRTGRs. 2,817.02 crLetter of Acceptance Issued to ContractorAwarded
Package 6Civil Works – Tunnels & StationsM/S J.Kumar-CRTGRs. 2,118.40 crLetter of Acceptance Issued to ContractorAwarded
Package 7Civil Works – Tunnels & StationsL&T-STEC JVRs. 2,281.45 crLetter of Acceptance Issued to ContractorAwarded
Package 8Civil – DepotSAM (INDIA) BUILTWELL PVT LTDRs. 328.26 crLetter of Acceptance Issued to ContractorAwarded
Package 9Plant & Equipment for Depot--No JICA concurrence required for the packages as per Loan Agreement Schedule 4 Sect. 3 Cl. No. 3 (JICA letter dtd: 26-06-18)-
Package 10BMM3-CBS-TWK-02 (Package 10-B) Part Design, Procurement and Supply, Installation, Testing and Commissioning of ballastless Track on the Mainline from BKC station (excluded) to Cuffe Parade station (included) excluding the procurement and supply of Head Hardened rail 60 E1 (UIC 60), 1080 grade HH, Turnouts, Scissor Crossovers and Buffer Stops for Mumbai Metro Line 3 (Colaba – Bandra – SEEPZ). Part Design, Procurement and Supply of Rail Fasteners System for the ballastless Track for the Mainline including Contract Package 10 A for Mumbai Metro Line 3 (Colaba – Bandra – SEEPZ).M/s LARSEN & TOURBO LIMITED (India)Rs.303.27 crLetter of Acceptance Issued to ContractorAwarded
Package 10CMM3-CBS-TWK-03 (Package 10C) Part Design, Procurement and Part Supply, Installation, Testing and Commissioning of Ballastless Track on the Mainline from Aarey station (excluded) until BKC station (included) and Ballasted Track in the area of at-grade Aarey Station and in the Depot area of Mumbai Metro Line 3 (Colaba – Bandra – SEEPZ) and Procurement and Supply of Turnouts, Scissor Crossovers and Buffer Stops for the entire Mainline for Mumbai Metro Line 3 (Colaba – Bandra – SEEPZ) including Package 10 B.M/s LARSEN & TOURBO LIMITED (India)Rs. 229 crLetter of Acceptance Issued to ContractorAwarded
Package 10DMM3-CBS-TWK-04 (Package 10 D) Supply of 8490 MT Head Hardened (HH) Rails (UIC 60E1, IRS-T-12:2009, 1080 grade) for Track Work of Mumbai Metro Line 3 (Colaba-Bandra -SEEPZ) Rail Project.M/s Mitsui & Co. LIMITED (Japan)Rs. 53.47 crLetter of Acceptance Issued to ContractorAwarded
Package 11ATraction Works

CONSORTIUM OF ALSTOM TRANSPORT INDIA LTD & ALSTOM TRANSPORT S.A.

Rs. 272.43 cr

Letter of Acceptance Issued to Contractor

Awarded
Package 11BPower Supply Works

M/s LARSEN & TOURBO LIMITED 

Rs. 338.37 cr

Letter of Acceptance Issued to Contractor

Awarded
Package 12Signaling & Train control, PSD, Telecommunication System and M&E SCADACONSORTIUM OF ALSTOM TRANSPORT INDIA LTD & ALSTOM TRANSPORT S.A., FRANCE-

Letter of Acceptance Issued to Contractor

Awarded
Package 13Station Security System----
Package 14Automatic Fare CollectionCONSORTIUM OF M/S. ASIS ELECTRONIK VE BILLISIM SISTEMLERI  A.S., TURKEY AND KALINDEE RAIL NIRMAN-A DIVISION OF TEXMACO RAIL & ENGINEERING LIMITED, INDIA (KALINDEE - ASIS JV)-

Letter of Acceptance Issued to Contractor

Awarded
Package 15Tunnel Ventilation & Environmental Control System

M/s Shanghai Tunnel Engineering Co. Ltd - Phase-1

M/s Blue Star Limited - Lot-1 of Phase-2

M/s Voltas Limited - Lot-2 of Phase-2

-

Letter of Acceptance Issued to Contractor for Phase-1

Letter of Acceptance Issued to Contractor for Lot-1 of Phase-2

Letter of Acceptance Issued to Contractor for Lot-2 of Phase-2 .

Awarded
Package 16AEscalator Works

Lot E2: Johnson- SJEC Consortium

Lot E1: Yuanda- Royal Consortium

-

Lot E2: Letter of Acceptance Issued to Contractor 

Lot E1:Letter of Acceptance Issued to Contractor

Awarded
Package 16BElavator/Lift Works

Lot L2: Yuanda-Royal Consortium

Lot L1: Joint Venture of IFE and Cranex

-

Lot L2: Letter of Acceptance Issued to Contractor

Lot L1: Letter of Acceptance Issued to Contractor

Awarded
Package 17Rolling StockCONSORTIUM OF ALSTOM TRANSPORT INDIA LTD & ALSTOM TRANSPORT S.A.-

Letter of Acceptance Issued to Contractor

Awarded
Package 18General Consultant--General Consultants engaged.-

Operation and Maintenance contract status:

Sr. No.Particulars of WorkName of the PartyTenureWork Order AmountIssued Date
1MM3-CBS-O&M “Operations and Maintenance Services for Mumbai Metro Line - 3”Delhi Metro Rail Corporation10 years16,21,00,00,000.0026th May 2023
2Provision of Ticket Vending Services and Customer Care Service Staff at Metro Stations & Associated Locations (Package-1: Aarey JVLR to Bandra Station of MML-3).M/s SIS Limited4 years49,27,70,558.3014th May 2024
3Mechanized Cleaning & Housekeeping Works from SEEPZ to Bandra Metro Station (09 Stations) at Line-3 of MMRCL. (Package 2)All Services Global Private Limited4 years42,47,66,527.5415th May 2024
4Cleaning of Rolling Stock (Metro Train) & RRV and Mechanized Cleaning & Housekeeping Works of Sariput Nagar RSS, Aarey metro Station, & Aarey Depot premises at Line-3 of MMRCL.(Package 1)M/s. A-1 Facility and Property Managers Private Limited.4 years36,75,39,853.0721st June 2024
5Provision of DOG Squad including Sniffer DOG with Handler, Caretaker, Supervisor & Trainer at Mumbai Metro Line-3 of MMRCLM/s. Force One Dog Security4 years4,74,58,023.1521st June2024
6Insurance of Passengers, Public, Assets, Cyber- Crime risk, Terrorism, Properties and Trains of Mumbai Metro Line-3M/s. Go Digit General Insurance Ltd.1 years6,39,80,000.0005th October 2024
MMRC

Recent News

mmrc
Mumbai 2025 : A city reborn
+31 Dec 2024
Mumbai's big infra leap
+31 Dec 2024
वांद्रे स्थानकातून मेट्रो स्थानक-बीकेसी बससेवा सुरू
+19 Dec 2024
दोन हजारांहून अधिक झाडांचे 'जिओ टॅगिंग' पूर्ण
+13 Dec 2024
आरे ते बीकेसीदरम्यान मुंबईच्या पोटातून सुसाट प्रवास !
+3 Dec 2024
जपानच्या उच्चाधिकाऱ्यांची बीकेसी मेट्रो स्थानकाला भेट
+02 Sep 2024
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros
MMRC
  • mmrc
  • mmrc
  • mmrc
  • mmrc
MMRC

MMRC © 2019. All rights are reserved.

Maintained by Best IT Company in Ludhiana

  • mmrc
  • mmrc
  • mmrc
  • mmrc
Top