Skip to main content
  • Accessibility And Screen Reader Options
  • English
  • मराठी
  • हिन्दी

A A A

Homepage Logo Mumbai Metro Rail Corporation Ltd. (JV of Govt. of India and Govt. of Maharashtra)

mmrc

Search form
Home MMRC
  • Home
  • About MMRC
    • Know Your Metro
    • Our Vision, Mission & Values
    • Board of Directors
    • Key Management Team
    • Our Organization
    • Managing Director
    • Reports & Documents
    • MOA & AOA
    • Annual Report
  • Project
    • Project Route
    • Project Timeline
    • Project Funding
    • Illustrative Designs
    • Technology
    • Typical Utility Shifting Plan
    • Project Consultants
    • Benefits of Metro Line 3
    • Environmental Benefits
    • Rehabilitation & Resettlement (R&R)
      • FLGRC/SLGRC
      • Public Consultation
      • Final BSES
      • Lottery Result
      • Policy / Project Documents
      • In - situ R&R Office Address
      • BSES Survey Maps
      • Building wise Allotment List
      • Rehabilitation Building Occupation Certificate
      • Public Notices
    • Projects Reports & Documents
    • NOC
    • Notice
    • Typical Traffic Diversion Plan
  • People Connect
    • FAQ
      • FAQ on Kalbadevi & Girgaon
      • FAQ on Aarey
    • Facts Of Aarey
      • Note On Aarey
      • MMRC Ad
    • Quick Facts
  • Tenders
    • Civil
    • System
      • Electrical
      • Signalling & Telecom
      • Rolling Stock
      • IT
      • Depot (M&P)
      • O & M
    • Planning
    • Miscellaneous
    • Awarded Contracts
    • MMRC Contractors
    • eTender
    • eTender - CPPP
    • EOI-MoHUA
  • Media
    • Gallery
      • Photo Gallery
      • Video Gallery
    • News
    • Newsletters
    • MD Speaks
    • Press Releases
    • Social Media
      • Facebook
      • Instagram
      • Twitter
      • Youtube
  • Careers
    • Recruitment
    • Internship Policy
  • RTI
    • RTI (GOI)
    • RTI (GOM)
    • RTI ACT 2005
    • RTI/SANAD
    • PIO/APIO
  • Vigilance
    • Chief Vigilance Officer
    • About MMRC Vigilance
    • Functions of the CVO
    • Vigilance Complaints
    • Notice
    • Contact Us
    • Vigilance Awareness Week
  • Contact Us
    • How to reach us
    • Compliance Officer & Company Secretary
  • Policies
    • RISK ASSESSMENT & MANAGEMENT POLICY
    • WHISTLE BLOWER POLICY
    • CORPORATE SOCIAL RESPONSIBILITY POLICY
Flash News
MMRC

Flash News

MMRC E-Calendar 2025
Design, Engineering, Supply, Installation, Testing, Commissioning and Comprehensive Operation & Maintenance of Roof Top Solar PV Project and associated support structure works on RESCO Model for a Period of 25 Years on Aarey Station & Depot Buildings of Mumbai Metro Line -3 (MML-3) Project.
MMRC extends service hours for election day
Implementation of Multi Modal Integration Facilities at Six Underground Metro Stations viz. BKC, Bandra Colony, Santacruz, Chatrapati Shivaji Maharaj Domestic Airport (CSIA T1), Sahar Road & Chatrapati Shivaji Maharaj International Airport (CSIA T2) of Mumbai Metro Line ‐ 3
Implementation of Multi Modal Integration Facilities at Six Underground Metro Stations viz. BKC, Bandra Colony, Santacruz, CSIA T1, Sahar Road & CSIA T2 of Mumbai Metro Line-3 project
Implementation of Multi Modal Integration Facilities at Six Underground Metro Stations viz. BKC, Bandra Colony, Santacruz, Chatrapati Shivaji Maharaj Domestic Airport (CSIA T1), Sahar Road & Chatrapati Shivaji Maharaj International Airport (CSIA T2) of Mumbai Metro Line ‐ 3
List of NOC's issued till 30.09.2024
Property Development on Plot bearing CTS No 1987, 1988 at Nariman Point, A Ward, Mumbai (Maharashtra, India) on Long-Term Lease Basis
Invitation to Roadshow for Property Development on plot bearing CTS No. 1987, 1988 at Nariman Point, A Ward, Mumbai (Maharashtra, India) on Long-term Lease Basis
Supplying & fixing precast SFRC heavy duty slab for inspection pathways in Aarey colony car depot of Mumbai Metro Line ‐3 project
  1. Home
  2. Package
  3. Weekly progress report for package-3
mmrc icon

Weekly progress report for package-3

MMRC

Updated as on: 31st May 2022

Sr. No

Nature of Work

Status

1

Barricading

100 % completed. In progress with the construction works.

2

Rehabilitation & Resettlement

Completed.

3

Traffic Diversion

Completed.

4

Geo-technical investigation

100% completed.

5

Building condition Survey

Completed.

6

Tunneling Progress

Science Museum- Worli (Tansa-1) – 1382/ 1382 rings has been erected. (100 % completed)

Science Museum- Worli (Tansa-2) – 1372 / 1372 rings has been erected. (100 % completed)

 

Science Museum-Mumbai Central (Tansa-2) – 1182 / 1308 rings has been erected. (90.36 % Completed)

Science Museum-Mumbai Central (Tansa-1) – 792 / 1303 rings has been erected. (60.78 % Completed)

7

Segment Production Progress

100 % of the total scope of permanent rings has been completed.

8

Secant Piling Progress

Station Box Area:

 

Mumbai Central – 100 % completed

Mahalaxmi – 100 % completed

Science Museum – 100 % completed

Acharya Atre Chowk –100 % completed

Worli – 100 % completed

9

Traffic Decking & King Posts

 

Mumbai Central –100 % has been completed.

Mahalaxmi – 100 % has been completed.

Acharya Atre Chowk- 100 % has been completed.

Worli – 100 % has been completed.

 

 

 

10

Excavation (Station Box)

Mumbai Central:

2,14,164 / 2,14,164  cu.m ( 100% ) has been completed.

 

Mahalaxmi:

1,66,229 / 1,66,229 cu.m ( 100%) has been completed.

 

Science Museum :

2,11,816 / 2,11,816 cu.m ( 100 %) has been completed.

 

Acharya Atre Chowk:

1,87,375 / 1,87,375  cu.m ( 100 % ) has been completed.

 

Worli:

1,77,370 / 1,77,370 cu.m ( 100% ) has been completed.

 

 

11

Base Slab Progress

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100% of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

100 % of the total scope has been completed.

 

Worli:

100 % of the total scope has been completed.

 

12

Concourse Slab Progress

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100 % of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

87 % of the total scope has been completed.

 

Worli:

98 % of the total scope has been completed.

 

 

13

Roof Slab Progress

 

Mumbai Central:

100 % of the total scope has been completed.

 

Mahalaxmi:

100 % of the total scope has been completed.

 

Science museum:

100 % of the total scope has been completed.

 

Acharya Atre Chowk:

58 % of the total scope has been completed.

 

Worli:

97 % of the total scope has been completed.

 

  14

Platform Slab Progress

Mumbai Central:

68 % of the total scope has been completed.

 

Mahalaxmi:

20 % of the total scope has been completed.

 

Science museum:

69 % of the total scope has been completed.

 

Acharya Atre Chowk:

39 % of the total scope has been completed.

 

Worli:

57 % of the total scope has been completed.

 

 

MMRC

Recent News

mmrc
Mumbai 2025 : A city reborn
+31 Dec 2024
Mumbai's big infra leap
+31 Dec 2024
वांद्रे स्थानकातून मेट्रो स्थानक-बीकेसी बससेवा सुरू
+19 Dec 2024
दोन हजारांहून अधिक झाडांचे 'जिओ टॅगिंग' पूर्ण
+13 Dec 2024
आरे ते बीकेसीदरम्यान मुंबईच्या पोटातून सुसाट प्रवास !
+3 Dec 2024
जपानच्या उच्चाधिकाऱ्यांची बीकेसी मेट्रो स्थानकाला भेट
+02 Sep 2024
MMRC

About MMRC

  • Tenders
  • Project
  • News
  • Contact Us
  • eTender
MMRC

Helpful Information

  • Project Route
MMRC

Policy

  • MMRC Green Policy
  • Disclaimer
  • Privacy Policy
MMRC

Other Govt Sites

  • Govt of India
  • MoHUA
  • Indian Railways
  • Govt of Maharashtra
  • MMRDA
  • Other Metros
MMRC
  • mmrc
  • mmrc
  • mmrc
  • mmrc
MMRC

MMRC © 2019. All rights are reserved.

Maintained by Best IT Company in Ludhiana

  • mmrc
  • mmrc
  • mmrc
  • mmrc
Top